The rule: patient testing stops immediately when a rejection rule is violated — and resumes only when control values are back in control.

1 · Start of shift

Yes — in control: QC is verified within acceptable limits. Proceed with testing; patient results are authorized and released.

2 · Warning rule only

Key distinction: a warning rule alone does not stop the run — a rejection rule does. When a rejection rule is violated, follow column 3.

3 · Rejection rule — stop & fix

Run QC at shift start
→
All in limits? → test
→
Warning → inspect run
→
Rejection → STOP
→
Fix + fresh QC
→
Resume — or recall